Baosight completes Shanghai Metro Line 12 basic control design
2012-06-01 10:51:33
Summary:After months of effort, undertaken by Baosight, the Shanghai Metro Line 12 three basic systems basic design have been fully completed.
After months of effort, undertaken by Baosight, the Shanghai Metro Line 12 three basic systems basic design have been fully completed. In the recently held first project design contact meeting, it passes rigorous examination from owners and engineering design experts participating in the construction.
Line 12 is the rail transit in building in Shanghai with largest investment and longest expanse across regions currently. It starts from Minhang District Qishen Station in west and ends in Pudong New Area Gimhae Road Station in the east, with more than 40 kilometers in length. When it is completed, it will become the longitudinal southwest northeast axial trunk in downtown.
To apply the concept of green energy from the beginning, the owners raise construction requirements in the design of the monitoring system for the task unit, that they should build the first real operation-oriented energy-saving demonstration line, science and technology demonstration line and intelligent stations.
Line 12 is also Baosight first Shanghai rail transit project undertaking. Since it wins three monitoring systems project bidding in November 2011, Baosight deploys key personnel and carries out joint research targeted at difficulties such as numerous transfer stations on Line 12, short system design time and complex interface.
With the collaboration among owners, the two sides design institutes and supervision, three monitoring systems design task is completed with quality and efficiency. This shows Baosight's powerful comprehensive strength in the large rail traffic monitoring system integration technology and it wins the owner' praise.
Line 12 is the rail transit in building in Shanghai with largest investment and longest expanse across regions currently. It starts from Minhang District Qishen Station in west and ends in Pudong New Area Gimhae Road Station in the east, with more than 40 kilometers in length. When it is completed, it will become the longitudinal southwest northeast axial trunk in downtown.
To apply the concept of green energy from the beginning, the owners raise construction requirements in the design of the monitoring system for the task unit, that they should build the first real operation-oriented energy-saving demonstration line, science and technology demonstration line and intelligent stations.
Line 12 is also Baosight first Shanghai rail transit project undertaking. Since it wins three monitoring systems project bidding in November 2011, Baosight deploys key personnel and carries out joint research targeted at difficulties such as numerous transfer stations on Line 12, short system design time and complex interface.
With the collaboration among owners, the two sides design institutes and supervision, three monitoring systems design task is completed with quality and efficiency. This shows Baosight's powerful comprehensive strength in the large rail traffic monitoring system integration technology and it wins the owner' praise.
Key Words:Baosight,Metro,Shanghai